单项选择题
Perfect工程建设项目中各工序历时如下表所示,则本项目最快完成时间为______周。同时,通过______可以缩短项目工期。
工序名称 |
紧前工序 |
持续时间(周) |
A |
— |
1 |
B |
A |
2 |
C |
A |
3 |
D |
B |
2 |
E |
B |
2 |
F |
C、D |
4 |
G |
E |
4 |
H |
B |
5 |
I |
G、H |
4 |
J |
F |
3 |
The project schedule is more than a document that lays out the
activities over time to represent the time dimension of the project, it is a
management tool to be used for decision making. As such, the schedule is used by
the project management team to ______.
A. Measure, delay, record, distribute, analyze, and direct
B. Plan, schedule, monitor, control, report, and forecast
C. Promote, highlight, monitor, control, forecast, and report
D. Emphasize, visualize, analyze, conceptualize, report and record