单项选择题

The()provides the project manager with the authority to apply organizational resources to project activities.

A.project management plan
B.contract
C.project human resource plan
D.projectcharter


你可能感兴趣的试题

2.单项选择题

The()defines the phases that connect the beginning of a project to its end.

A.schedule
B.project life cycle
C.temporary
D.milestone

3.单项选择题

()means that every project has a definite beginning and a definite end.

A.Projectphase
B.Unique
C.Temporary
D.Closure

7.单项选择题

 The()technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

A.costaggregation
B.reserve analysis
C.parametricestimating
D.funding limit reconciliation