单项选择题

A FastT Host FC-2 bus adapter, a U320 SCSI adapter, and three 10/100Mb Ethernet adapters have to be installed as optimally as possible.  This is going to be a 24X7 system.  The addition of extra PCI-cards is a major consideration as well.  Based on the following, what is the best configuration?()
(1)Slot 1  66MHz  Bus 1      
(2)Slot 2  66MHz  Bus 1      
(3)Slot 3 100MHz  Bus 2      
(4)Slot 4 100Mhz  Bus 2      
(5)Slot 5 133Mhz  Bus 3      
(6)Slot 6 133Mhz  Bus 3

A.Put the Ethernet adapters in slots 1, 2 and 3. Put the FastT HBA in slot 5. Put the U320 adapter in slot 6.
B.Put the Ethernet adapters in slots 1, 4 and 6. Put the FastT HBA in slot 5. Put the U320 adapter in slot 3.
C.Put the Ethernet adapters in slots 1, 2 and 4. Put the FastT HBA in slot 3. Put the U320 adapter in slot 5.
D.Put the Ethernet adapters in slots 1, 2 and 3. Put the FastT HBA in slot 5. Put the U320 adapter in slot 4


您可能感兴趣的试卷

你可能感兴趣的试题

1.单项选择题Which of the following is a function of the XceL4 Cache?()

A.It places frequently accessed data close to the processor to help deliver faster performance.
B.It replaces L3 cache memory.
C.It speeds up processor performance by purging the current set of instructions and freeing them up to work on the next set of instructions.
D.It allows the system to address more than 16GB of memory.

2.单项选择题Which of the following statements applies to the x445 memory subsystem?()

A.With XA-32 architecture, addressing more than 64GB of RAM can be installed.
B.The amount of memory should be balanced across ports for best performance.
C.All DIMM slots should be populated in numerical order - slot 1 before slot 2, slot 2 before slot 3, etc.
D.All even number DIMM slots should be populated before odd number DIMM slots.

4.单项选择题A customer needs a new database server.  The database application has a high memory overhead but does not benefit from 8-way processing.  They would like a rack mountable system, which will support four Xeon processors with 512KB of L2 cache and 16GB of main system memory.  Which of the following will satisfy the customer’s requirements?()

A.x445 with four Xeon DP processors and 16GB of memory in a single SMP module
B.x445 with four Xeon MP processors and 16GB of memory in a single SMP module
C.x445 with two SMP modules each containing two Xeon DP processors and 8GB of memory
D.x445 with two SMP modules each containing two Xeon MP processors and 8GB of memory

5.多项选择题Which TWO of the following are required to use the hot-swap memory feature of the x445 while being operating system independent?()

A.Memory Mirroring must be enabled in the BIOS.
B.Redundant bit steering must be enabled in the BIOS.
C.DIMMs must be the same size and speed as the DIMMs being replaced.
D.Memory Mirroring must be enabled in the operating system.
E.DIMMs can be of same size or larger or same speed or faster.

7.单项选择题Which memory technology combination on the x255 will allow for two memory banks to fail while maintaining the server?()

A.Memory mirroring and hot swap memory
B.Memory mirroring and hot spare memory
C.Four way memory interleaving and chipkill
D.Four way memory interleaving and memory mirroring

8.单项选择题Some xSeries servers support 4-way memory interleaving and some support 2-way interleaving.  In both types of interleaving, the data is accessed 256 bits at a time.  How is this 256-bit data access achieved with 2-way interleaving?()

A.The DIMMs used for 2-way interleaving are double the width of DIMM used in 4-way interleaving.
B.The DIMMs used for 2-way interleaving are 64-bit wide and data bits are accessed both on the rising edge and falling edge of the clock cycle.
C.The DIMMs used for 2-way interleaving are 32-bit wide and data bits are accessed both on the rising edge and falling edge of the clock cycle.
D.The DIMMs used for 2-way interleaving are double the width and data bits are accessed both on the rising edge and falling edge of the clock cycle.

9.单项选择题A customer uses an IBM xSeries x366.  They experienced downtime when the NIC failed earlier this year.  Their Windows 2003 server needs to be accessible all the time, at the highest speed possible.  Two adapters are currently installed in the x366.  Which of the following is the procedure to obtain the best performance and ensure network functionality in case of NIC failure?()

A.Install four NICs and configure load balancing adapter teaming.
B.Install four NICs and configure adapter failover teaming.
C.Install seven NICs and configure load balancing adapter teaming.
D.Install one extra NIC to team with the internal adapter and configure failover teaming.

最新试题

A customer wants to hold all enterprise data on their DS4000 system.  Several servers were added after they purchased another company.  The servers that have to be run are:      (1)An Oracle database running on a HP-UX server  (2)Several virtual machines running on VMWare ESX server      (3)A Microsoft cluster running Exchange 2000 server  Which of these new servers can be integrated with the DS4000?()

题型:单项选择题

A startup company recently lost their critical database due to hardware failure on a Windows 2003 4-way processor server running 32-bit applications and an out-dated backup due to a narrow backup window.  To prevent this situation from happening again, the solution proposed must be cost effective, scale to 16-way and allow for future storage expansion.  Which TWO of the following options should the consultant recommend?()

题型:多项选择题

Which of the following statements applies to the x445 memory subsystem?()

题型:单项选择题

A customer needs to deploy a SAN and connect nine servers running a mix of Windows and Linux.  They currently need 12TB, but their growth requirements will be tripled in the near future.  They will also consolidate 18 legacy Windows servers onto one system using virtualization software and connect that server to the storage solution.  A DS4000 series backup solution needs to be included in the design.  Which of the following solutions will satisfy these requirements?()

题型:单项选择题

A customer purchased a new IBM xSeries x445.  They already have a non-IBM industry standard rack with 14U of open space that is being considered to house the new server.  The rack houses an existing UPS unit for the entire rack.  Which of the following questions is most important to ensure that the power in the datacenter environment is ready for the initial install?()

题型:单项选择题

An online retailer is considering deploying a database application on xSeries and Windows to serve their Web-based transactions. The database will need about 4TB of usable storage.  Downtime costs the customer tens of thousands of dollars per minute, so system availability will be of highest priority.  The customer needs to acquire the system within a certain budget but will pay for things that provide higher system availability.  Which of the following will be the most appropriate solution?()

题型:单项选择题

A company wants to run multiple applications on an x445 to serve their user base.  OS and application licensing cost is a factor. Which TWO questions will help the specialist decide on the operating environment and the number of processors per server?()

题型:多项选择题

A customer has a requirement for a server to run Windows Server 2003 Enterprise Edition and Exchange 2003 Enterprise Edition. It has been determined that 4GB RAM will be needed.  The customer is trying to decide between the two following configurations:  (1)An IBM xSeries x366 with 4 Xeon MP processors and 4 x 1GB memory DIMMs.      (2)An IBM xSeries x445 with 4 Xeon MP processors and 8 x 1GB memory DIMMs. Which question should be asked to guide the customer in selecting the correct memory configuration?()

题型:单项选择题

A small bio-technical company is interested in implementing a 32-node Linux cluster.They have developed their own software that allows all of the nodes to work on the same problem at the same time.The application requires messages to be passed between the nodes.Each node will require access to a shared storage pool of around 500GB. To identify the inter-process communication (IPC) networking requirements, which of the following is the most appropriate question to ask?()

题型:单项选择题

A company installed a new server to manage its electronic image storage.  They have two distinct image sizes: 2KB and 16KB.  Two distinct arrays are created on a ServeRAID adapter.  The first array will store all of the 2KB images, and the second array will store all the 16KB images.  The RAID stripe size was left at the default size of 8KB.  After installation, a performance problem is identified. According to performance monitoring, 80% of the images are 16KB.  Which of the following will best optimize performance?()

题型:单项选择题