Project X has an internal rate of return of 20 percent. Project Y has an internal rate of return of 15 percent. Both projects have a positive net present valuE. Which of the following statements is most correct? ( )
A.
Project X must have a higher net present value than Project Y.
B.
If the two projects have the same WACC, Project X must have a higher net present value.
C.
Project X must have a shorter payback than Project Y.
D.
Statements b and c are correct.
E.
None of the statements above is correct.