单项选择题

A TQM team at Narton Corp has recorded the following average times for production:
   Wait           3.0 days      Move     0.5 days
   Inspection  0.4 days      Queue   9.3 days
   Process     0.2 days
What is the throughput time, Manufacturing Cycle Efficiency (MCE), and delivery cycle time (DCT)?
A、10.4 days; 1.9%; 13.4 days
B、0.2 days; 1.9%; 0.7 days
C、4.1 days; 52.0%; 13.4 days
D、13.4 days; 5.1%; 10.4 days