The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.

A.estimating
B.defining
C.planning
D.sequencing


你可能感兴趣的试题

1.单项选择题

The () describes, in detail, the project's deliverables and the work required to create those deliverables.

A.project scope statement
B.project requirement
C.project charter
D.product specification

2.单项选择题The()provides the project manager with the authority to apply organizational resources to project activities.

A.project management plan
B.contract
C.project human resource plan
D.project charter

5.单项选择题

The() defines the phases that connect the beginning of a project to its end.

A.schedule
B.project life cycle
C.temporary
D.milestone

6.单项选择题

()means that every project has a definite beginning and a definite end.

A.Project phase
B.Unique
C.Temporary
D.Closure

7.单项选择题

() is one of the quality planning outputs.

A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist

8.单项选择题

The inputs of developing project management plan do not include()

A.project charter
B.stakeholder management strategy
C.project scope statement
D.outputs from planning processes

9.单项选择题

Which of the following statement related to PMO is not correct?()

A.The specific form, function, and structure of a PMO are dependent upon the needs of the organization that it supports.
B.One of the key features of a PMO is managing shared resources across all projects administered by the PMO.
C.The PMO focuses on the specified project objectives.
D.The PMO optimizes the use of shared organizational resources across all projects.

最新试题

()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.

题型:单项选择题

()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.

题型:单项选择题

Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

题型:单项选择题

()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

题型:单项选择题

The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

题型:单项选择题

Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.

题型:单项选择题

In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including() .

题型:单项选择题

PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.

题型:单项选择题

The()provides the project manager with the authority to apply organizational resources to project activities.

题型:单项选择题

The() defines the phases that connect the beginning of a project to its end.

题型:单项选择题