单项选择题

Which of the following statement related to PMO is not correct?()

A.The specific form, function, and structure of a PMO are dependent upon the needs of the organization that it supports.
B.One of the key features of a PMO is managing shared resources across all projects administered by the PMO.
C.The PMO focuses on the specified project objectives.
D.The PMO optimizes the use of shared organizational resources across all projects.


你可能感兴趣的试题

1.单项选择题

Which of the following statement related to PMO is not correct?()

A.The specific form, function, and structure of a PMO are dependent upon the needs of the organization that it supports.
B.One of the key features of a PMO is managing shared resources across all projects administered by the PMO.
C.The PMO focuses on the specified project objectives.
D.The PMO optimizes the use of shared organizational resources across all projects.

2.单项选择题

() is one of the quality planning outputs.

A.Scope base line
B.Cost of quality
C.Product specification
D.Quality checklist

最新试题

In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.

题型:单项选择题

()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.

题型:单项选择题

On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and () are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

题型:单项选择题

() is one of the quality planning outputs.

题型:单项选择题

The()provides the project manager with the authority to apply organizational resources to project activities.

题型:单项选择题

()is a category assigned to products or services having the same functional use but different technical characteristics. It is not same as quality.

题型:单项选择题

空白(1)处应选择()

题型:单项选择题

()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

题型:单项选择题

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

题型:单项选择题

Project Quality Management must address the management of the project and the() of the project. While Project Quality Management applies to all projects, regardless of the nature of their product, product quality measures and techniques are specific to the particular type of product produced by the project.

题型:单项选择题