单项选择题

Project () Management includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

A.Integration
B.Scope
C.Configuration
D.Requirement


你可能感兴趣的试题

8.单项选择题

The () describes, in detail, the project's deliverables and the work required to create those deliverables.

A.project scope statement
B.project requirement
C.project charter
D.product specification

9.单项选择题The()provides the project manager with the authority to apply organizational resources to project activities.

A.project management plan
B.contract
C.project human resource plan
D.project charter

最新试题

The() defines the phases that connect the beginning of a project to its end.

题型:单项选择题

()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

题型:单项选择题

空白(1)处应选择()

题型:单项选择题

The inputs of developing project management plan do not include()

题型:单项选择题

PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.

题型:单项选择题

() are individuals and organizations that are actively involved in the project, or whose interests may be affected as a result of project execution or project completion.

题型:单项选择题

()involves comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance. These other projects can be within the performing organization or outside of it, and can be within the same or in another application area.

题型:单项选择题

空白(2)处应选择()

题型:单项选择题

In the project management context,() includes characteristics of unification, consolidation, articulation, and integrative actions that are crucial to project completion, successfully meeting customer and other stakeholder requirements, and managing expectations.

题型:单项选择题

The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.

题型:单项选择题