单项选择题

A customer wants to implement the following Blades in BladeCenter H:Two POWER Blades running IBM i partitions.Two POWER Blades running AIX and LinuxFour x86 Blades running Windows.
Which of the following design consideration statements is correct?()

A.The Blades must use the same CIOv and CFFh expansion adapter types.
B.Two physical BladeCenter H chassis will be required. One for the POWER Blades, the other for the x86  Blades.
C.The x86 Blades and POWER Blades may use different expansion adapters provided the POWER Blades  are in bays 1-7 and the x86 Blades are in slots 8-14.
D.The x86 Blades and POWER Blades may use different expansion adapters, provided the corresponding I/O modules to Blade midplane connections are configured in the Advanced Management Module (AMM).


您可能感兴趣的试卷

你可能感兴趣的试题

1.单项选择题Which of the following items in a single enclosure Power 770 improves Reliability, Availability, and Serviceability?()

A.Redundant system clocks
B.Redundant service processors
C.eDRAM chips have redundant L3 cache
D.Main memory DIMMs contain a redundant DRAM chip

2.单项选择题Which of the following has an integrated database?()

A.AIX
B.IBM i
C.Linux
D.VIO Server

3.单项选择题Which of the following configuration is valid for expansion drawers on a Power 750 with 2 processor board sinstalled?()

A.3 PCI-e I/O drawers and 1 PCI-X I/O drawer
B.4 PCI-e I/O drawers and 4 RIO-2 I/O drawers
C.2 PCI-e I/O drawers and 4 PCI-x I/O drawers
D.4 PCI-e I/O drawers and 2 PCI-X I/O drawers

4.单项选择题

A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which  also has two Power 595s and five Power 750s, taking the total number of systems to 17. All currently installed  systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs.
How can they manage the new machines for the least cost?()

A.Purchase a second HMC and use this to manage the new servers.
B.Connect all of the new servers to the existing private HMC network.
C.Configure a second private network on their existing HMC for the new servers.
D.Connect 9 of the new servers to the existing HMC and use Integrated Virtualization Manager on the 10th.

5.单项选择题

A customer has 4 application and 2 database servers that will be installed in partitions on a Power 750. They are concerned that the database software vendor will charge based on every processor core in the server.
Which action will reduce the potential vendor software costs?()

A.Create capped partitions for the database servers.
B.Create workload partitions for the database servers.
C.Create a separate shared processor pool for the database servers.
D.Create virtual processors equal to the entitlement for database servers.

7.单项选择题

A system administrator has been instructed to attach storage in their client LPARs, in a Power 770, with fibre channel adapters using N_port ID virtualization (NPIV).
Which of the following partitions has the minimum requirements to utilize virtual fibre channel?()

A.LPAR-A with 1Gb FC HBA and SAN connection
B.LPAR-B with 2Gb FC HBA and SAN connection
C.LPAR-C with 4Gb FC HBA and SAN connection
D.LPAR-D with 8Gb FC HBA and SAN connection

8.单项选择题

A customer has shut down an LPAR after using DLPAR to add or remove processor and memory resources. When the partition is reactivated, the desired changes are missing.
What action, or sequence of actions, will immediately and permanently solve this problem?()

A.Add or remove the resources in the profile, click 'apply', then 'save'.
B.Add or remove the resources using DLPAR and change the partition profile.
C.Add or remove the resources using DLPAR, then shutdown and reactivate the LPAR.
D.Add or remove the resources in the system profile and reboot the managed system.

最新试题

A company plans to deploy a two-enclosure, 23-core Power 780 system with AIX, IBM i and Linux in thefollowing configuration: 3 AIX partitions with dedicated network and disk adapters; 1 native IBM i partition acting as a host1 hosted IBM i partition; 2 hosted Linux partitions.Which configuration will provide boot disk capability to all partitions?()

题型:单项选择题

Which of the following uses compression/decompression to increase the memory available for client workloads?()

题型:单项选择题

Which of the following items in a single enclosure Power 770 improves Reliability, Availability, and Serviceability?()

题型:单项选择题

How can resource allocations for an active partition on a Power 750 be changed immediately and permanently?()

题型:单项选择题

A customer has a Power 750 with the following: One processor card with 8 cores enabled, and 64GB RAM installed One GX+ adapter with one I/O drawer attached; One 4-port 1Gbps IVE adapterPowerVM Standard Edition; They need to add a GX++ adapter and cable it to an I/O drawer.Which of the following must also be ordered?()

题型:单项选择题

A POWER7 processor has L1, L2 and L3 caches. Which of the three caches uses embedded DRAM (eDRAM) technology?()

题型:单项选择题

A customer has an LPAR with 4 dedicated cores on a POWER7 server with SMT4 enabled. How many logical processors are presented to an application running on this LPAR?()

题型:单项选择题

Ancustomer with limited storage management skills needs a disk subsystem with up to 70TB capacity and enterprise class performance. Which disk storage system should be recommended?()

题型:单项选择题

A data center includes a Power 750 server running AIX and Linux, and PS700 Blades running AIX. What can the customer use to update AIX and Linux, create and deploy LPARs, and set energy caps for both servers from a single console?()

题型:单项选择题

A customer is deploying a new database on a PS701 Blade in a BladeCenter H, and requires redundant network and SAN adapters. Which configuration supports the customer requirement?()

题型:单项选择题