单项选择题Which of the following uses compression/decompression to increase the memory available for client workloads?()

A.PowerVM
B.VMControl
C.Active Memory Sharing
D.Active Memory Expansion


您可能感兴趣的试卷

你可能感兴趣的试题

8.单项选择题Which system provides the highest performance per core, and the least cost for applications licensed per core?()

A.A Power 795 withMaxCore mode
B.A Power 780 withMaxCore mode
C.A Power 755 withTurboCore mode
D.A Power 780 withTurboCore mode

9.单项选择题

A customer wants to implement the following Blades in BladeCenter H:Two POWER Blades running IBM i partitions.Two POWER Blades running AIX and LinuxFour x86 Blades running Windows.
Which of the following design consideration statements is correct?()

A.The Blades must use the same CIOv and CFFh expansion adapter types.
B.Two physical BladeCenter H chassis will be required. One for the POWER Blades, the other for the x86  Blades.
C.The x86 Blades and POWER Blades may use different expansion adapters provided the POWER Blades  are in bays 1-7 and the x86 Blades are in slots 8-14.
D.The x86 Blades and POWER Blades may use different expansion adapters, provided the corresponding I/O modules to Blade midplane connections are configured in the Advanced Management Module (AMM).

10.单项选择题Which of the following items in a single enclosure Power 770 improves Reliability, Availability, and Serviceability?()

A.Redundant system clocks
B.Redundant service processors
C.eDRAM chips have redundant L3 cache
D.Main memory DIMMs contain a redundant DRAM chip

最新试题

Which operating system can directly host managed storage for IBM i, AIX, Linux, VMware and Windows on a Power Systems server?()

题型:单项选择题

A data center includes a Power 750 server running AIX and Linux, and PS700 Blades running AIX. What can the customer use to update AIX and Linux, create and deploy LPARs, and set energy caps for both servers from a single console?()

题型:单项选择题

A customer has an LPAR with 4 dedicated cores on a POWER7 server with SMT4 enabled. How many logical processors are presented to an application running on this LPAR?()

题型:单项选择题

A retail customer has an 8-core Power 740 server with 2 partitions. Production has 4 dedicated cores and the test partition has 2 dedicated cores. Both partitions run during the day without problems. At night, batch processing is exceeding the run window.Which solution addresses this problem without requiring additional  hardware?()

题型:单项选择题

A customer requires their application to have high availability within a data center, and also the ability to recover at a data center located 600km away in the event of an outage.Which system software solution component supports the customer requirement?()

题型:单项选择题

A system is being designed with many LPARs which will be clients of dual VIO Servers. The VIO Servers must be redundant so that, in the event of scheduled maintenance, the clients do not need to be shut down.Which of these strategies could be used to ensure that the client LPARs continue to be able to use the network in the event of a VIO Server being shut down?()

题型:单项选择题

A customer would like to configure an uncapped LPAR so that it can use 2 to 8 cores depending on the workload characteristics. With SMT4 enabled, what is the least amount of processing resources which can be configured for the LPAR?()

题型:单项选择题

An end user is deploying Blade servers to replace obsolete rack mounted servers. In addition to AIX Web server and database workloads, they also have Windows workloads.Which Blade is designed for Windows workloads?()

题型:单项选择题

A Power 720 customer using IVM wants to implement dual VIO servers, but is unable to create the second server. What is the most likely reason for this?()

题型:单项选择题

Which of the following is a compelling reason to deploy IBM Systems Director Active Energy Manager (AEM) in a data center with high energy utilization?()

题型:单项选择题