Your project is behind schedule due to conflict between team members . Havingresolved the conflict, to get the project back on schedule , you should consider ().
A.crashing the schedule
B.performing resource leveling
C.conducting reverse resource allocation scheduling
D.utilizing the critical chain resources
您可能感兴趣的试卷
你可能感兴趣的试题
An example of scope verification is ().
A.review the performance ofan installed software module
B.managing changes to the project schedule
C.decomposing the WBS to a work package level
D.performing a benefit/cost analysis to determine if we should proceed with the project
The TCP protocolis a ()layer protocol.
A.physical
B.network
C.transport
D.application
The connection between two networks from an intemet is handled by a machine known as a()
A.bridge
B.server
C.router
D.switch
The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.
A.users
B.servers
C.producers
D.suppliers
There are strategies typically deal with threats or risk that may have negative impacts on project objectives if they occur, some other strategies are suggested to deal with risks with potentially positive impacts. ()is a risk response strategy that may be adopted for either threats or opportunities.
A.share
B.Mitigate
C.Transfer
D.Acceptance
A ()is a collection of projects and other work that are grouped together to facilitate effective management ofthat work to meet strategic business objectives.
A.program
B.portfolio
C.projectoflargesize
D.PMO
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
A.Benchmarking
B.Quality metric
C.Quality checklist
D.Brainstornung
Contract closeout is a process that involves()
A.Customer satisfaction analysis and final payment
B.Administrative closeout and archiving records
C.Finial contractor payment and Lessons learned
D.Product verification and administrative closeout
In which form of projects origination would the project manager be likely to exercise the most control over Project resources.()
A.Strongmatrix
B.Projectized
C.Projectcoordinator
D.Weakmatrix
最新试题
空白(2)处填()
Quality planning tools are often used to help plan effective quality management activities . ()is one of such tools, which involves company actual or planned project practices to those or other projects to generate ideas for improvement and to provide a basis by which to measure performance.
空白(2)处填()
Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()
空白(2)处填()
空白(3)处填()
空白(3)处填()
The parties to government procurement refer to the principal entities of all kinds that enjoy rights and undertake obligations in government procurement, including the procuring entities, the ()and the procuring agencies.
空白(4)处填()
The TCP protocolis a ()layer protocol.