A.Hardware InfoCenter
B.System Planning Tool
C.Offering Information website
D.Technical Delivery and Assessment Guide
您可能感兴趣的试卷
你可能感兴趣的试题
A.4
B.8
C.16
D.32
A retail customer has an 8-core Power 740 server with 2 partitions. Production has 4 dedicated cores and the test partition has 2 dedicated cores. Both partitions run during the day without problems. At night, batch processing is exceeding the run window.
Which solution addresses this problem without requiring additional hardware?()
A.AddingVMControl will automate processor resource allocation during peak workloads.
B.Enable Dynamic Symmetric Multithreading in the HMC to balance workloads across processors.
C.Add processing resources during the times they are required using Utility Capacity on Demand.
D.Changing the partitions to Uncapped can make use of additional processor cycles during peak workloads.
A system is being designed with many LPARs which will be clients of dual VIO Servers. The VIO Servers must be redundant so that, in the event of scheduled maintenance, the clients do not need to be shut down.
Which of these strategies could be used to ensure that the client LPARs continue to be able to use the network in the event of a VIO Server being shut down?()
A.ImplementPowerHA SystemMirror on both VIO servers.
B.ConfigureEtherchannel between the client LPARs and the two VIO servers
C.Configure Network Interface Backup between the two VIO servers and use each VIO server to access the network.
D.Implement Shared Ethernet Adapter failover and have all client partitions access the network through the shared adapters.
A.L3 only
B.L1 and L2
C.L2 and L3
D.L1, L2 and L3
A customer has an HMC-managed Power Systems server with 6 partitions. Four production partitions are subject to varying workloads throughout the day, and two are used for development and testing. The production applications have different licensing limitations on the number of physical cores that may be used. The development partitions can use no more than 1 core. The customer would like to dynamically optimize processor utilization within the licensing limits, with minimal operator intervention.
Which of the following meets the customer requirement?()
A.Define the production partitions' maximum CPU to the licensing limitations. Define the development/test partition maximums to one core. Configure each partition to be capped.
B.Define the production partitions' maximum CPU to the licensing limitations. Define the development/test partition maximums to one core. Configure each partition to be uncapped.
C.Define the production partitions' maximum CPU to the licensing limitations. Define the development/test partitions to use no more than one core. Configure the HMC scheduler to dynamically assign processors among the pools over a day.
D.Create a shared processor pool for each production partition, with the maximum processor limit set to the licensing limit for the application in the pool. Assign the development and testing partitions to a processor pool with a maximum of 1 core. Configure each partition to use uncapped processing.
A.DS6800
B.DS8100
C.DS8300
D.XIV Storage System
A.Removes the requirement for Intelligent PDUs
B.Monitor and balance disk speeds according to utilization needs
C.Is a required element forEnergyStar certification of the server/data center
D.Monitor and report power and thermal trending to optimize energy consumption "Pass Any Exam. AnyTime." - 14 IBM 000-106: Practice Exam
A.JS21
B.JS23
C.PS700
D.PS701
A customer has a Power 750 with the following: One processor card with 8 cores enabled, and 64GB RAM installed One GX+ adapter with one I/O drawer attached; One 4-port 1Gbps IVE adapterPowerVM Standard Edition; They need to add a GX++ adapter and cable it to an I/O drawer.
Which of the following must also be ordered?()
A.A second IVE adapter
B.A second processor card
C.PowerVM Enterprise Edition
D.An additional cable-management arm
A company plans to deploy a two-enclosure, 23-core Power 780 system with AIX, IBM i and Linux in thefollowing configuration: 3 AIX partitions with dedicated network and disk adapters; 1 native IBM i partition acting as a host1 hosted IBM i partition; 2 hosted Linux partitions.
Which configuration will provide boot disk capability to all partitions?()
A.Use dual-split backplane in both enclosures for the three AIX partitions and the IBMi partition.
B.Put each partition on a dedicated controller using the triple-split backplane option in both enclosures.
C.Use the triple-split backplane option in one enclosure for the AIX partitions, and the default dual-split backplane for the IBMi partition in the second enclosure.
D.Use the triple-split backplane option in one enclosure for the AIX partitions, and the non-split backplane mode in the second enclosure for the IBMi hosting partition.
最新试题
A customer plans to consolidate several systems onto POWER7. Their immediate requirement is to have a single Power 770, and they will buy a second Power 770 at a later stage. They want to keep their existing three POWER5 570s and three POWER6 520s which are all managed by an HMC (7310-CR3).Which of these statements is true and would minimize the cost?()
A customer wants to implement the following Blades in BladeCenter H:Two POWER Blades running IBM i partitions.Two POWER Blades running AIX and LinuxFour x86 Blades running Windows.Which of the following design consideration statements is correct?()
A Power 720 customer using IVM wants to implement dual VIO servers, but is unable to create the second server. What is the most likely reason for this?()
Using the following information: Performance data from an existing system that a new system will replace; Performance estimates that anticipate future workloads; Micro-partitioning and logical partitioning implementations.Which of the following allows a technical sales representative to create a system design which can be imported into an HMC?()
A data center includes a Power 750 server running AIX and Linux, and PS700 Blades running AIX. What can the customer use to update AIX and Linux, create and deploy LPARs, and set energy caps for both servers from a single console?()
A POWER7 processor has L1, L2 and L3 caches. Which of the three caches uses embedded DRAM (eDRAM) technology?()
A customer plans to consolidate two 8-core POWER6 systems with a total of 8 PCI-X adapters, 6 PCIe adapters, and a PCI-X I/O drawer into a 16-core Power 750.Which action allows the most efficient use of existing equipment?()
Which system provides the highest performance per core, and the least cost for applications licensed per core?()
Which of the following uses compression/decompression to increase the memory available for client workloads?()
A customer has a 4-core POWER6 570 with 4 partitions and a 2-port 1Gbps Integrated Virtual Ethernet (IVE) Adapter. They are having problems with throughput on the Ethernet adapter and want to improve performance.Which of the following solutions will help the customer with this issue for the least cost and with the least interruption?()