单项选择题

Estimating activity durations uses information on activity scope of(),required resource types, estimated resource quantities, and resource calendars.

A.milestone
B.baseline
C.quality
D.work


你可能感兴趣的试题

2.单项选择题

Define Activities is the process ofidentifying the specific actions to be performed toproduce the()

A.projectelements
B.work drafts
C.workpackage
D.projectdeliverables

5.单项选择题

()involves using mathematical techniques to forecast future outcomes based onhistorical results.

A.Trendanalysis
B.Qualityaudit
C.Defect repair review
D.Flowcharting

10.单项选择题

The()process analyzes the effect of risk events and assigns a numerical rating to those risks.

A.Riskldentification
B.Quantitative RiskAnalysis
C.Qualitative RiskAnalysis
D.Risk Monitoring and Control