A.IBM Grid Toolbox
B.IBM Capacity on Demand
C.IBM Cluster Systems Management
D.IBM Global Solutions Directory
您可能感兴趣的试卷
你可能感兴趣的试题
A.IBM p5-570 8-way
B.IBM p5-570 4-way
C.IBM p5-570 2-way
D.IBM p5-570 16-way
A.Micro-Partitioning support and the L3 controller is now between L2 and main memory.
B.Dynamic partitioning support and the L3 controller is now between L2 and main memory.
C.Micro-Partitioning support and the L3 controller is no longer between L2 and main memory.
D.Dynamic partitioning support and the L3 controller is no longer between L2 and main memory.
A.Create a POWER5 technical presentation for the account executive’s use.
B.Mentor the account executive with the most important POWER5 features and benefits.
C.Attend the meeting instead of the account executive to present the POWER5 features and benefits.
D.Join the meeting via teleconference at a prescheduled time to present the POWER5 features and benefits.
A.The technical support specialist has completed a UNIX course at college.
B.The technical specialist has supported several similar projects and has earned an IBM AIX certification.
C.The technical support specialist’s company sells $3M of UNIX computer systems every year.
D.The technical support specialist has sold and installed at least a dozen Apple and iSeries systems with POWER processors.
A.One 7311-D20 drawer
B.Two 7311-D20 drawers
C.Two 7311-D10 drawers
D.One 7311-D10 drawers
A.Sales Manual
B.Announcement Letter
C.Site and Hardware Planning Information
D.Adapter, Devices, and Cable Information for Multiple Bus Systems
A.7311-D20 drawer with four disks
B.Upgrade to AIX 5.3
C.Fiber adapters to attach to SAN
D.Nothing
A customer is considering multiple options for a particular set of workloads on AIX v5.2.
They need to run ten identical LPARS, each containing four fibre cards, two 2-port Ethernet cards, and one SCSI card as well as two internal boot disks.
They want the LPARS to be split across two physical systems for redundancy purposes; cost is an issue.
They need a total of approximately 40 rPerf for all ten workloads. Which of the following solutions best fits these needs?()
A.2 x p655 1.7ghz 8-way servers (21.87 rPerf each)
B.2 x p670 1.5ghz 8-way servers (24.18 rPerf each)
C.2 x p690 1.7ghz 8-way servers (27.11 rPerf each)
D.2 x p650 1.45ghz 8-way servers (18.67 rPerf each)
A.Voltage
B.Frequency
C.Power Source Loading (max)
D.Power Source Loading (typical)
最新试题
A customer wants to upgrade an existing pSeries system. In addition to retrieving the IBM configuration records, what else should be done to ensure an accurate upgrade quote is provided?()
During a presentation on the p5 machines, a customer asks the pSeries technical specialist a question regarding the differences between POWER4+ and POWER5. In addition to new advanced power management, SMT, and larger L2 and L3 caches in POWER5, which of the following describes some of the key improvements in POWER5?()
A customer has a large UNIX environment and has engaged a pSeries technical specialist to work on a solution with them. Which of the following statements would best establish UNIX credibility with a knowledgeable customer?()
A customer wants a configuration for a new system that includes Reserve CoD. Which of the following systems would be the most appropriate to configure for them?()
A pSeries technical specialist is configuring the network adapters for an HACMP cluster. The plan is to use a four-port Ethernet adapter with IPAT via IP aliasing for the two service IP labels. Which of the following would be a critical concern with the proposed configuration?()
A customer has a failing HBA adapter and needs to identify the location of the adapter. Which of the following AIX commands should the specialist recommend the customer review?()
Due to slow response times, a customer purchased additional memory. After the memory was installed,response time was not improved. They complained to the pSeries technical specialist. Which of the following questions should be asked of this customer?()
A customer is planning to migrate a financial application to a 12-way p5-570 system with 96GB of memory. The application data is stored on an ESS Model 800 attached to a p670 server with AIX 5.2. They will have a short outage window to perform the data migration. What is the quickest way to move all the data stored on the attached ESS from the p670 to the new p5-570?()
A customer wants to receive automatic notification of critical software problems and fixes for their RS/6000 or eServer pSeries system. Which is the most appropriate services offering to recommend to them?()
A customer is experiencing problems with a failed disk drive on their newly purchased p630 server. The IBM CE has replaced the disk and now the mirrored Logical Volume needs to be re-created. The customer does not have the skills to do this. There is no support contract with the solution provider but the p630 is covered under a Software Maintenance Agreement (SWMA) 24/7 contract. What should the pSeries technical specialist do first?()