单项选择题If the organizational spending plan has allocated $100,000 for a project, and the high level budget estimate for that project is $200,000; which of the following is accurate?()

A.The high level budget estimates are inaccurate
B.The organizational spending plan is inaccurate
C.The budget is not aligned with the spending plan of the organization
D.The detailed bottom up budget will need to be adjusted


您可能感兴趣的试卷

你可能感兴趣的试题

1.单项选择题What is the role of the line manager in a project plan?()

A.Provide resources to a project
B.Request requirements changes
C.Resolve team conflicts
D.Control the project budget

2.单项选择题Team member listing, scheduled tasks, and risk identification are part of the:()

A.project plan.
B.project charter.
C.communication plan.
D.WBS (Work Breakdown Structure).

3.单项选择题Why is it important to have a final meeting on a project that has been cancelled?()

A.Document lessons learned
B.Assign responsibility
C.Close budget
D.Begin new project

4.单项选择题Who is responsible for authorizing closure of the project?()

A.Project Manager
B.Stakeholder
C.Customer
D.Executive Sponsor

5.单项选择题Acceptance of deliverables to multiple locations requires which type of sign off?()

A.Design Acceptance
B.Code Acceptance
C.Module Acceptance
D.Site Acceptance

6.单项选择题The last deliverable at the Close Out meeting is:()

A.source code.
B.passwords.
C.lessons learned.
D.test results.

10.单项选择题After upgrading a server motherboard to the latest firmware revision, configuring LAN access in the SSU (System Setup Utility) fails. Which action should be taken FIRST to correct this problem?()

A. replace the NIC
B. install the latest SSU (System Setup Utility) version
C. upgrade the firmware on the NIC
D. assign the NIC a static IRQ in the SSU (System Setup Utility)

最新试题

Which action increases server availability?()

题型:单项选择题

Which RAID standard combines data striping across drives with mirroring?()

题型:单项选择题

Which backup solution is the MOST appropriate for backing up a payload from a corporation with multiple servers and approximately 300 GB of data?()

题型:单项选择题

The SOW (Statement of Work) is another name for the:()

题型:单项选择题

Which type of server is responsible for resolving NetBIOS names?()

题型:单项选择题

The project sponsor wants the project manager to develop and implement Quality Management techniques to ensure a smooth project transition to the deployment phase. What is an appropriate Quality Management technique to implement?()

题型:单项选择题

What is the role of the line manager in a project plan?()

题型:单项选择题

Which throughput does a 33 MHz, 33-bit bus have?()

题型:单项选择题

Why is it important to have a final meeting on a project that has been cancelled?()

题型:单项选择题

Team selection is not just a function of finding someone whos a technical or administrative expert. What will a project sponsor leading a high visibility project look for in a project manager?()

题型:单项选择题